Yeronga State School – New Administration and Learning Centre (Dental Building Refurbishment)

From design inception to execution, we demonstrate skilful mastery at every stage of our delivery

From design inception to execution, we demonstrate skilful mastery at every stage of our delivery

Year completed

2022, 15 months

Service

Project Management, Quantity Surveying

Value

$9,800,000 excl GST

Builder

Kane Constructions

Architect

Towill Design Group

Location

Yeronga, Brisbane

The Challenge

The project team faced a significant challenge in converting a former dental clinic into an educational facility with a staff hub, nine classrooms, and a Resource Centre. The old structure’s age led to unexpected issues, impacting the budget and requiring careful cost planning. The central construction site on the main road disrupted school traffic, necessitating clear communication with the community. Complications arose during the COVID-19 pandemic, causing delays due to restrictions and difficulty securing trades. Despite these obstacles, the builder demonstrated resilience, delivering a fully operational facility by Term 3, 2022.

The Solution

The successful transformation of an old dental clinic into a modern learning centre was achieved through effective collaboration between Project Managers, Architects, the School, and the Department of Education, emphasising a solid commitment to sustainability.

The project created a functional and visually appealing space by closely aligning the design with the school’s vision and values. It exemplified the environmental and economic advantages of adaptive reuse in educational infrastructure. Proactive communication strategies, including regular updates to the community, helped address potential disruptions and build positive relationships with the school and neighbouring residents.

Despite unforeseen challenges, the project management team demonstrated adaptability by implementing contingency plans, conducting risk assessments, and adjusting schedules during the COVID-19 pandemic. Their proactive approach, including transparent communication and meticulous monitoring, was pivotal in ensuring the project’s success despite changes to the original timelines.